Proposed 500km electricity superhighway between Peterhead and Yorkshire receives provisional £3.4billion funding package

A PROVISIONAL funding package of £3.4billion has been announced for a proposed subsea and underground 500km electricity superhighway between Scotland ...

Facebook
LinkedIn
X

A PROVISIONAL funding package of £3.4billion has been announced for a proposed subsea and underground 500km electricity superhighway between Scotland and Yorkshire which could power up to 2million homes. 

Eastern Green Link 2 (EGL2) is a proposed 2GW high voltage electricity ‘superhighway’ cable link between Peterhead in Aberdeenshire and Drax in North Yorkshire. Most of the cable (around 436km) will be under the North Sea with the remaining 70km buried underground onshore. Two converter stations, one at each end of the cable, are planned to help feed the electricity transported by the cable into the grid and from there onto consumers.  

Subscribe to our daily newsletter

Why? Free to subscribe, no paywall, daily business news digest.

Designed to help harness the potential of Britain’s offshore wind power, EGL2 is the second project so far to proceed under Ofgem’s new fast track Accelerated Strategic Transmission Investment (ASTI) framework. Earlier this month the first ASTI project, Eastern Green Link 1 (EGL1) another subsea link between England and Scotland received a provisional £2billion funding package. 

ASTI  is designed to speed up the delivery of strategic energy projects, enabling more electricity generated by offshore wind to be delivered to British consumers. The new framework accelerates the project funding process by up to two years. EGL2 is one of 26 projects identified as critical to meeting the Government’s target of 50GW of offshore wind capacity by 2030 and included in Ofgem’s ASTI cohort.  

The project is financed by the developers with costs later recouped through bills. To ensure consumer costs are minimised Ofgem has scrutinised the costs proposed by the developers under the ASTI process. It has identified £67million that could be cut from indirect costs without impacting project delivery or quality. 

Delivery of projects such as EGL2 will not only provide millions of consumers with access to homegrown wind energy, by boosting grid capacity it will further benefit consumers by cutting compensation paid to generators currently asked to turn off production, during times of high wind, due to lack of grid capacity.   

Rebecca Barnett, Ofgem Director of Major Projects, said:   

“To ensure we meet future energy demand and achieve Government net zero targets we must speed up the expansion of the high voltage electricity network which connects consumers to homegrown energy.” 

“Eastern Link 2 is the second project to reach this stage under our new Accelerated Strategic Transmission (ASTI) process which has been designed to boost Britain’s energy security by unlocking investment and speeding up the delivery of major power projects.”  

She added: “However just because we’ve streamlined the approval process doesn’t mean we’re handing developers blank cheques. The ASTI framework helps ensure consumers are protected from unnecessary costs and we make budget adjustments where we don’t see maximum efficiency and benefit for consumers.” 

 The proposed budget is now subject to a consultation published today (Wednesday 27 March).  Feedback on the proposed budget can be sent to: [email protected]  

 The consultations are due to close on Friday  26th April. Ofgem will consider all responses and will publish a decision on next steps on its website at ofgem.gov.uk/consultations.  

 To view the consultation document, click here

 The project is also subject to it securing future planning permission in a process overseen by the Planning Inspectorate.  

Related Articles

Major new study uncovers greatest safety leadership risks facing energy sector
Energy Institute spotlights outstanding students with annual competition
Pioneering Scottish floating offshore wind farm project hits major milestone
Aberdeen energy firm delivers solar power solution for Aker BP’s unmanned installation
North-east students empowered for future energy careers through industry mentorship and skills development
UK’s largest proposed wind farm trapped in two-year planning delay

Other Articles from ABN